Western Transbay Transit Center Site (Between First and Second Streets): This weekend there is no construction work scheduled.
Central Transbay Transit Center Site (Between Fremont and First Streets): This weekend there is no construction work scheduled.
Eastern Transbay Transit Center Site (Between Beale and Fremont Streets): This weekend there may be demolition work on surface level concrete on Saturday June 15 between the hours of 8:00 AM and 5:00 PM. No construction work is currently schedueled for Sunday June 16.
Weekday Work (6/17/13 – 6/21/13):
Night Shift:
Excavation and Internal Bracing Work:
Western Transit Center Site (Between First and Second Streets): This week Tuesday June 18th there will be equipment set-up at night. The concrete pour will be performed between the hours of 6:00 AM- 9:00 PM . This week general maintenance of equipment and site clean-up is scheduled Monday through Friday between the hours of 6:00 AM and 11:30 PM. Trucks will enter from the construction gate located on Howard Street (between First and Second Streets) and exit the construction gate at First Street (between Mission and Howard Streets).
Central Transit Center Site (Between Fremont and First Streets): Excavation and trucking will continue and is scheduled Monday through Friday between the hours of 6:00 AM and 2:30 AM the next day. Welding of the cross lot steel bracing is scheduled Monday through Friday between the hours of 6:00 AM and 11:30 PM. Trucks will enter from the construction gate located on Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).
Eastern Transit Center Site (Between Beale and Fremont Streets): Excavation and trucking will continue and is scheduled Monday through Friday between the hours of 6:00 AM and 2:30 AM the next day. Welding cross lot steel bracing scheduled Monday through Friday between the hours of 6:00 AM and 11:30 PM. Trucks will enter from the construction gate located on Fremont Street (between Mission and Howard Streets) and exit the construction gate at Beale Street (between Mission and Howard Streets).
Day Shift:
Excavation and Bracing/Below Grade Transit Center Construction:
Western Transit Center Site (Between First and Second Streets): This week, on Tuesday June 18th, the contractor will pour a concrete mud slab beginning at 6:00 AM continuing until 9:00 PM. Installation and testing of Geothermal Piping and Micropiles continues Monday through Friday between the hours of 6:00 AM to 6:30 PM. General maintenance of equipment and clean-up of excavation and trucking is scheduled Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Howard Street (between First and Second Streets) and exit the construction gate at First Street (between Mission and Howard Streets).
Central Transit Center Site (Between Fremont and First Streets): This week micropiles will be installed between the hours of 6:00 AM and 6:30 PM. This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM and 2:30 AM the next day. Welding of cross lot steel bracing is scheduled from Monday through Friday between the hours of 6:00 AM and 11:30 PM. The contractor will be off-hauling soil 24-hours a day during this time. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).
Eastern Transit Center Site (Between Beale and Fremont Streets): This week demolition of the surface level concrete will be performed day shift only Monday through Friday between the hours of 7:00 AM to 9:00 PM resulting in increased vibration and noise. Excavation and trucking is scheduled Monday through Friday between the hours of 6:00 AM and 2:30 AM the next day. Welding of cross lot steel bracing is scheduled Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Fremont Street and exit the construction gate at Beale Street (between Mission and Howard Streets).
Underground Utilities/Trenching Work:
Mission Street (Between Beale and Second Streets): There will be underground utilities work and traffic lane closures daily, Monday through Friday between 9:00 AM and 3:00 PM.
What to Expect Next Weekend (6/22/13 – 6/23/13):
Western Transit Center Site (Between First and Second Streets): This weekend there is no construction work scheduled. However; dependent on the progress of the contractor construction may be performed Saturday June 22, between 8:00 AM and 5:00 PM. This weekend there is no construction work scheduled for Sunday June 23.
Central Transit Center Site (Between Fremont and First Streets): This weekend micropiles will be installed Saturday June 22 between the hours of 8:00 AM and 5:00 PM. However; dependent on the progress of the contractor, additional construction may be performed Saturday June 22, between 8:00 AM and 5:00 PM. This weekend there is no construction work scheduled for Sunday June 23.
Eastern Transit Center Site (Between Beale and Fremont Streets): This weekend there is no construction work scheduled. However; dependent on the progress of the contractor construction including demolition surface level concrete will restart and be performed during the day shift only resulting in increased vibration and noise on Saturday June 23, between 8:00 AM and 5:00 PM. This weekend there is no construction work scheduled for Sunday June 22.
Detours, Street and Sidewalk Closures:
The following streets will be temporarily impacted due to project activities. So you can plan ahead, please review the affected streets below:
Beale Street (Between Mission and Howard Streets): Beale Street traffic may be impacted occasionally during construction with trucks exiting at the construction gates onto Beale Street. Construction flaggers will be assigned during peak ours to assist with traffic and pedestrians. Pedestrians will continue to use east sidewalk between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.
Fremont Street (Between Mission and Howard Streets): Fremont Street traffic may be impacted occasionally during construction with trucks entering and exiting at the construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross. NOTE: The Fremont Street temporary bridge traffic signal will be activated mid block between Mission and Howard Streets at the Fremont Street Bridge and construction access trestle intersection in June 2013.
First Street (Between Mission and Howard Streets): First Street traffic may be impacted occasionally during construction with trucks entering and exiting construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.
Natoma Street (Between Fremont and First Streets): Natoma Street (between Fremont and First Streets) has been reduced to one lane, one way (west bound), all vehicles will enter from Fremont Street and exit at First Street. Local vehicle and pedestrian access will remain available.
Natoma Street (Between First and Second Streets): Natoma Street (between First and Second Streets) has been changed to a dead end street for the life of the project with no vehicle access through Natoma Street from Second Street. Local vehicle and pedestrian access will remain available.
Minna Street (Between First and Second Streets): Minna Street has been reduced to one lane, one way (west bound), all vehicles will enter from First Street and exit at Second Street. There will be no parking along Minna Street between First Street and 130 feet east of Second Street for the life of the project. Local vehicle and pedestrian access will remain available.
Mission Street (Between First and Second Streets): There will be underground utilities work and traffic lane closure daily, Monday through Friday between 9:00 AM and 3:00 PM.
Howard Street (Between Fremont and Second Streets): Howard Street traffic may be impacted occasionally during construction with trucks entering and exiting the construction gate at Howard Street (between First and Second Streets). Construction flaggers will be assigned during peak hours to assist with traffic and pedestrians.
Community Meeting: AC Transit Proposed Bus Staging
AC Transit is operating from the Transbay Temporary Terminal during construction of the future Transbay Transit Center. AC Transit uses a lot near the terminal and on‐street parking areas to stage its buses in preparation for the evening commute Monday through Friday from 3 p.m. to 7 p.m. A new construction project scheduled to begin this fall will require AC Transit to vacate the parking lot it is currently using and find another alternative.
In an effort find an alternative staging location, AC Transit has consulted with the Transbay Joint Powers Authority and the San Francisco Municipal Transportation Agency (SFMTA) to evaluate potential staging options. A public meeting will be held to present this proposal and request public comment on Thursday, June 20, 2013, at 6 p.m., at 201 Mission Street, Suite 2100.
Stay tuned.
Zennie Abraham | Zennie Abraham or “Zennie62” is the founder of Zennie62Media which consists of zennie62blog.com and a multimedia blog news aggregator and video network, and 78-blog network, with social media and content development services and consulting. Zennie is a pioneer video blogger, YouTube Partner, social media practitioner, game developer, and pundit. Note: news aggregator content does not reflect the personal views of Mr. Abraham.