Transbay-Transit-Center-9San Francisco TransBay Terminal Project Construction Update.

Here’s the latest San Francisco TransBay Terminal Project Construction Update:

10 Day Look Ahead: Construction Activities

Friday, March 22, 2013 – Sunday, March 31, 2013

NOTICE – STREET CLOSURE – BEALE STREET BRIDGE, APRIL 5-8: The third and final traffic bridge is scheduled to be installed on Beale Street, between Mission and Howard Streets, the weekend of April 5-8. Beale Street will close to through at 8:00 PM and will reopen Monday morning at 5:00 AM.

This week at Transbay…

What to Expect This Weekend (3/23/13 – 3/24/13):

Eastern Transit Center Site (Between Beale and Fremont Streets): This weekend there is no construction work scheduled for Saturday, March 22 or Sunday, March 23.

Central Transit Center Site (Between First and Fremont Streets): This weekend there is no construction work scheduled for Saturday, March 22 or Sunday, March 23.

Western Transit Center Site (Between Second and First Streets): This weekend there is no construction work scheduled for Saturday, March 22 or Sunday, March 23.

Weekday Work (Monday 3/25/13 – Friday 3/29/13):

Night Shift:

Excavation and Internal Bracing Work:

Beale Street (Between Mission and Howard Streets): There will be bridge preparation work Monday through Friday with work scheduled from 6:00 AM to 11:30 PM. The Beale Street temporary bridge preparation has resulted in construction impacts with traffic lanes reduced from three lanes down to two until early April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates.

Eastern Transit Center Site (Between Fremont and Beale Streets):​ There will be construction access trestle preparation work Monday through Friday with work scheduled from 6:00 AM to 11:30 PM with excavation and trucking Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Fremont Street and exit the construction gate at Beale Street.

Fremont Street (Between Mission and Howard Streets): Fremont Street traffic will be impacted Monday and Tuesday nights with traffic lanes reduced from three lanes down to one between the hours of 10:00 PM and 5:00 AM to allow for the construction access trestle and bridge piers to be transported and unloaded at night. This transport at night is due to SFMTA regulations for oversized loads. Trucks will be loaded on Folsom Street near First Street and transported down Fremont Street and unloaded at the construction gate located on Fremont Street. Construction flaggers and SFPD 10B officers will be assigned during peak hours to assist with traffic and pedestrians.

Central Transit Center Site (Between First and Fremont Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Day Shift:

Excavation and Bracing/Below Grade Transit Center Construction:

The project’s internal steel bracing, excavation and trucking of soils has become a 24 hour activity with excavation down to an average depth of 60 to 65 feet. The excavation progresses from the west transit center site to the eastern end for the new Transbay Transit Center building and will continue through the end of 2014. The western zone excavation and bracing is in progress with a target completion of mid 2013, the below grade contractor will soon start construction of the lower level concrete foundation. The central Transit Center Site internal steel bracing, excavation and trucking of soils is in progress and continues until the end of 2013. The eastern Transit Center Site construction access trestle, excavation and trucking of soils have commenced and will continue into early 2014.

Beale Street (Between Mission and Howard Streets): There will be bridge preparation on the east side will work day and night Monday through Friday with work scheduled from 6:00 AM to 11:30 PM. Some demolition of the surface level concrete will be performed this week during the day shift. The Beale Street temporary bridge preparation has resulted in construction impacts with traffic lanes reduced from three down to two lanes until early April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates.

Eastern Transit Center Site (Between Beale and Fremont Streets): This week the drilled piers are being installed for future construction of the access trestle and to support excavation and bracing. Some demolition of the surface level concrete slab will be performed during the day shift resulting in vibration and noise. Trucks will enter from the construction gate located on Fremont Street (between Mission and Howard Streets) and exit the construction gate at Beale Street.

Central Transit Center Site (Between First and Fremont Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. and drilled Micropiles and welding of trestle steel and cross lot steel bracing is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Underground Utilities/Trenching Work:

Mission Street (Between Beale and Second Streets): There will be underground utilities work and traffic lane closures daily, Monday through Friday between 9:00 AM and 3:00 PM.

What to Expect Next Weekend (3/30/13 – 3/31/13):

Beale Street (Between Mission and Howard Streets): This weekend the Beale Street temporary bridge preparation work may be performed. The Beale Street work has resulted in construction impacts with traffic lanes reduced from three down to two lanes until early April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates. The Beale Street temporary bridge preparation activity requires closing of the east sidewalk between Mission Street and Howard Street until early April 2013. Pedestrians are to use the west sidewalk and are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

Eastern Transit Center Site (Between Beale and Fremont Streets): This weekend drilled piers for future construction access trestle may be performed Saturday March 30 between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. Trucks will enter from the construction gate located on Fremont Street and exit the construction gate at Beale Street.

Central Transit Center Site (Between First and Fremont Streets): This weekend excavation and trucking may be performed Saturday March 30 between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This weekend excavation, trucking, drilled Micropiles and welding of trestle steel and cross lot steel bracing may be performed Saturday March 30 between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Detours, Street and Sidewalk Closures:

The following streets will be temporarily impacted due to project activities. So you can plan ahead, please review the affected streets below:

Beale Street (Between Mission and Howard Streets): The Beale Street temporary bridge preparation has resulted in construction impacts with traffic with lanes reduced from three lanes down to two lanes until early April 2013. The Beale Street temporary bridge work requires closing of the east sidewalk between Mission Street and Howard Street until early April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Local access to 199 Fremont and 301 Mission only. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

NOTE: The Beale Street Temporary Traffic Bridge (Between Mission and Howard Streets) is scheduled to be installed April 5 and April 8, 2013. This temporary surface level bridge is the third and final bridge that will span the excavation site. Beale Street will be closed to traffic starting Friday, April 5, 2013 and re-open to traffic Monday morning, April 8, 2013.

Fremont Street (Between Mission and Howard Streets): Fremont Street traffic may be impacted occasionally during construction with trucks entering and exiting at the construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross. NOTE: The Fremont Street temporary bridge traffic signal will be activated mid block between Mission and Howard Streets at the First Street Bridge and construction access trestle intersection in March or April 2013.

First Street (Between Mission and Howard Streets): First Street traffic may be impacted occasionally during construction with trucks entering and exiting construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

Natoma Street (Between Fremont and First Streets): Natoma Street (between Fremont and First Streets) has been reduced to one lane, one way (west bound), all vehicles will enter from Fremont Street and exit at First Street. Local vehicle and pedestrian access will remain available.

Natoma Street (Between First and Second Streets): Natoma Street (between First and Second Streets) has been changed to a dead end street for the life of the project with no vehicle access through Natoma Street from Second Street. Local vehicle and pedestrian access will remain available.

Minna Street (Between First and Second Streets): Minna Street has been reduced to one lane, one way (west bound), all vehicles will enter from First Street and exit at Second Street. There will be no parking along Minna Street between First Street and 130 feet east of Second Street for the life of the project. Local vehicle and pedestrian access will remain available.

Mission Street (Between First and Second Streets): There will be underground utilities work and traffic lane closure daily, Monday through Friday between 9:00 AM and 3:00 PM.

Howard Street (Between Fremont and Second Streets): Howard Street traffic may be impacted occasionally during construction with trucks entering and exiting the construction gate at Howard Street (between First and Second Streets). Construction flaggers will be assigned during peak hours to assist with traffic and pedestrians.

Stay tuned.

By Zennie Abraham

Zennie Abraham | Zennie Abraham or "Zennie62" is the founder of Zennie62Media which consists of zennie62blog.com and a multimedia blog news aggregator and video network, and 78-blog network, with social media and content development services and consulting. Zennie is a pioneer video blogger, YouTube Partner, social media practitioner, game developer, and pundit. Note: news aggregator content does not reflect the personal views of Mr. Abraham.

Leave a Reply

Your email address will not be published. Required fields are marked *